Monday, October 9, 2017

1098.1- Main Spar- p.13-3 step 8 & p.13-5 step 1

Section 13: Main Spar- 5 hrs 26 mins (Main Spar 30:17, Wings 34:30Empennage 266:39, Total 321:07)
Rivet count: 20* (Total 5,767)

Lucky Chapter 13 is complete!! The numbers from my build log tracker tell me I worked 11 sessions averaging 2:45. Not too bad. It took about 7 weeks of actual building to do that. Now for the bad news. Unfortunately there was a two year break in the middle as discussed previously. So in reality, I averaged about 16 mins per week, or 2.5 minutes per calendar day. OK, now that I have entertained myself sufficiently...

The day started off well enough. I set up the spars for self-etching primer along the flanges (pic 1). I had been delaying that for a few days since it had been raining and humid, and I needed a well-ventilated garage. While I waited for the one side to dry before flipping over the other flange, I took care of some admin by annotating the parts I had "pulled" off of my inventory sheet. In the process of doing so, I realized I had not updated the empennage kit inventory the entire year I was in Mississippi. Good thing I had some time on my hands for that. After I flipped the spars and primed the other side and all the dings the main spar got in random spots, I started looking ahead to the next section for the wing ribs and I pulled those parts from inventory.

The primer will take 24 hours to fully set, but can be touched and handled after about 1 hour. All that remained was to rivet the AEX tie downs to the spars and prep the 823PP brackets and bolt them to the spars/AEX tie downs. I was on my last bolt for the night, and I have no clue what got into me, but I completely spaced on how tight I was turning the wrench and ended up collapsing one of the platenuts and shearing it (pic 3). Of course it happened on the last bolt!

So I removed the rest of the bolts, but the over-torqued one would not come out. After thirty minutes of trying everything I could think of, I busted out the #40 drill and went to work on the plate nut and the bolt together. I drilled through, rotated the bolt a 1/8 turn, and drilled again. I essentially cut the bolt in two with a drillbit. Not pretty by any means. Then I continued use of the drill by drilling out the ten rivets holding the AEX to the spar, so I could access the two rivets holding the now-split plate nut (pic 4). Then I re-riveted the plate nut to the AEX, and the AEX to the spar. So 32 rivets today, but only 20 of them count.

Mercifully, the second time around went better than the first, and after some bolt markings, chapter 13 is in the books (pic 2). I only have four days left of building before I have to take a two-month break for work, so I will work ahead with the ribs, and skip over anywhere that directs priming until January when I can order a fresh batch of AkZO. I don't expect to get very far this week, and I will likely spend most of my time fluting the ribs and deburring edges to be honest. So stay tuned for more updates! -M


 


Tuesday, August 29, 2017

1092- Tailcone- p.10-23 step 3-5 & p.10-24 step 1-3

Tailcone- 2 hrs 19 mins (Tailcone 89:52, Empennage 265:24, Total 286:20)
Rivet count: 0 (Total 5,321)

WOW! It's been over two years since my last post. So much has changed on blogger and youtube, and even more has changed in my own life. This post and the next one will actually be old videos and work that were done LESS than two years ago when I was still in MS. 

The last few weeks there were hectic with the move and I obviously never posted anything. We moved our household to NC, then spent 6 months in OK. We moved back to NC but lived in an apartment for a year and there was no chance of arranging space for a build. Then I deployed for 2 months, only to come back home and have a career change (a good kind, and one I was hoping for). That created 3 more months of living away from home for training. In the middle of that training, we had our second daughter which extended training by another month. So there is two years time accounted for in a single paragraph. 

I don't regret a single moment of it, as the past two years were spent ensuring a career path that will allow for the continued build of this project as well as growing a family to fly around in it! There's going to be a lot of technique and procedure that I will have to relearn as I move forward, but I'm sure it will be well worth it.

Anyways, on to the video! This represents the last steps in the construction of the tailcone. All assembly took place with bolts and clecos. There really isn't much to say about it. The video speaks for itself, and of course, I can't really remember much of the detail to be able to tell you about it anyways. 

TAILCONE COMPLETE!! (in just a hair under 90 hours of work...)


Wednesday, August 12, 2015

1091- Tailcone- p.10-22 step 1-3 & p.10-23 step 1-2

Tailcone- 4 hrs 48 mins (Tailcone 87:33, Empennage 263:05, Total 284:01)
Rivet count: 230 (Total 5,321)

This post is actually three days worth of work done a few weeks ago. I'm finally complete with pilot training!!!!!! so I'm catching up on administrative things such as updating this blog!!

In total, the top skin was attached and riveted to the stiffeners, longerons, and frames/bulkheads. That really sums it up! Some of the hardware was attached where the plans called for it. I noticed that I forgot to prime two pieces a few weeks back, so I am going to work ahead to chapter 13 of the wing spars and prime the two pieces along with those from the next chapter before jumping back and finishing up the tailcone with about an hour more of work. -M










This image is here for a question asked on vansairforce.com. Please ignore.



Monday, August 3, 2015

1090- Tailcone- p.10-21 step 1-5

Tailcone- 3 hrs 56 mins (Tailcone 82:45, Empennage 258:17, Total 279:13)
Rivet count: 203 (Total 5,091)

Famous last words indeed! Barely did anything this weekend since we spent Saturday in Huntsville, AL checking out space vehicles and rockets! We've actually got 3 nights worth of work here (Fri-Sun-Mon), even though last night barely counted with less than 30 minutes of work. We continue with assembly by riveting the nutplates to the bellcrank rib angles and then the angles to the bellcrank ribs. Then the ribs get cleco'd and riveted to the bottom skin and 1007 frame. 
We continue by riveting part of the longerons to the aft part of the side skins where they don't match with a skin. The aft deck gets cleco'd to the longerons as well as to the bulkheads and bracket/spacers. All of this is of course much easier said than done, particularly when some of the rivets have to be drilled out and re-done. We finished by riveting the 1009 frame (small piece) to the aft deck. We managed to place our 5,000th rivet today!!!
We'll continue tomorrow with the doubler. Lots of different sized rivets which means lots of adjustments and time consumption. However, once that is complete, we attach the aft top skin in place and start to rivet that! Then just a few more pieces in the forward part of the tailcone, and the tailcone is complete. -M


Wednesday, July 29, 2015

1089- Tailcone- p.10-20 step 2-7

Tailcone- 4 hrs 11 mins (Tailcone 78:49, Empennage 254:21, Total 275:17)
Rivet count: 483 (Total 4,888)

Lots of riveting today. Having a relatively lax day at work allowed me to spend quite some time on the project. I riveted the rest of the stiffeners to the side skin, and then all the bulkheads and frames to the skins. Then I did the aft bottom skin and the two stiffeners in the very aft part of the tailcone. This evening, -G came back to help otu and we knocked out the remaining rivets between the bottom skin and the side skins and the hard to reach rivets between the skins and frames at the curved part of the cone. We didn't do any of the F-1006 rivets since that happens after the fuselage is made, and we also skipped the longeron rivets since that won't happen until we get all the aft parts assembled and after we add the top skin. Tomorrow I'll continue with the small pieces and I hope to be done with the tailcone by this weekend. Famous last words, right? -M


Tuesday, July 28, 2015

1088- Tailcone- p.10-20 step 2 (part 2)

Tailcone- 1 hr 38 mins (Tailcone 74:38, Empennage 250:10, Total 271:06)
Rivet count: 311 (Total 4,405)

The riveting continues! -G came by to help out with riveting the stiffeners to the bottom skin. What a difference having another person helping. I highly recommend it. We did 1.25 times as many rivets in less than half the time. Tonight, I also had a bit of good luck. We started to rivet the side stiffeners from the aft end and immediately noticed the holes weren't quite in line. Had we started from the front, we wouldn't have noticed until after riveting a lot rivets. Turns out I had installed the D an E stiffeners in a swapped configuration. So it took nearly 30 minutes to disassemble half the side skin to swap the stiffeners and cleco everything back up. Smooth sailing from there. I'll finish up the stiffener-to-skin rivets tomorrow before moving on to the frame/bulkhead-to-skin rivets. -M


Monday, July 27, 2015

1087- Tailcone- p.10-20 step 2 (part 1)

Tailcone- 2 hrs 20 mins (Tailcone 73:00, Empennage 248:32, Total 269:28)
Rivet count: 246 (Total 4,094)

A milestone day! At 73 hours and counting, I've now spent more than 3 days and counting working on the tailcone. This also surpassed the 71 hour mark set while working on the elevators. The real milestone was in setting my 4,000th rivet! At an estimated 14-16,000 rivets on the project, that puts me at 1/4 of the way with the structure. That's not including the endless hours that will be spent on things like electrical, engine, interior, fiberglass, etc. (All the things without rivets) At 248-270 hrs, I'm roughly about 10% complete with the project! This is both super exciting and depressing that it has taken me nearly two years to get to this point with all the delays and stoppages due to work. More on that tomorrow hopefully. I'm waiting to hear back from a job-related assignment.

The video will show me riveting the the three stiffeners to the right skin. There's still and equal number of rivets on the left skin, and even more for the bottom skin. I have reached a point where I will have to recruit outside help for bucking. In theory, I could back rivet the stiffeners to the bottom skin, but I would imagine Van would have determined the proper building method for a reason, so I'll stick with the bucking bar for now. This one step is on pace to take 7 hours to accomplish. Onwards and upwards! -M


Thursday, July 23, 2015

1086- Tailcone- p.10-19 step 1-7 & p.10-20 step 1

Tailcone- 3 hrs 38 mins (Tailcone 70:40, Empennage 246:12, Total 267:08)
Rivet count: 73 (Total 3,848)

The first couple of hours we spent riveting together the remaining bulkheads and frames. Easy work, yet still time consuming. After that was done, I took a break for dinner, and was back at it. The back half of tonight's work was one step in the plans, but it consisted of assembling the tailcone back together. All I will say is that I'm happy that's done for the moment. Step two on page 20 begins the riveting of the skins. The rest of this page may take days if not weeks. -M


Monday, July 20, 2015

1085- Tailcone- p.10-17 step 5-6 & p.10-18 step 1-3

Tailcone- 2 hrs 19 mins (Tailcone 67:02, Empennage 242:34, Total 263:30)
Rivet count: 81 (Total 3,775)

The first 44 minutes of this entry is not in the video. I spent a little bit of time yesterday in the garage, but the heat was unbearable, so I stopped early. I assembled the battery case and all of its associated nutplates.
We begin riveting the tailcone itself by assembling the individual bulkheads. The 1012 and 1011 assemblies were done today. Pretty easy work, but very time consuming working with the small parts, and using the squeezer to get a nice looking product requires messing around with the settings in order to accomodate each different rivet type and size. We continue tomorrow with the 1010 bulkhead followed by the 1009, 1008, 1007, and 1006 frames. -M


Saturday, July 18, 2015

1084.2- Tailcone- p.10-17 step 3 (part 3)

Tailcone- 2 hrs 20 mins (Tailcone 64:43, Empennage 240:15, Total 261:11)
Rivet count: 0 (Total 3,694)

The priming is complete. Started the day off with a trip to Harbor Freight. Surprise win as I walked in and saw they sold gauges on their own for compressors. Figured I'd take a six dollar gamble that it was compatible instead of buying a $150 compressor and it worked! so the old compressor is back in business... Also, yesterday I spent some time looking into possibly getting a new HVLP gun, and I came across a few videos on youtube with a different way of setting it up than I had. Basically, I'm now shooting less volume but as a result using a narrower stream. Works really well for small parts and flanges. Not so well for skins, but it's still manageable. I was able to give two coats to all the parts not primed and give a touchup coat to the parts already primed, and I used a batch and a half of primer. So previously, I was wasting ALOT of primer as extra mist into the air. The downside is that some of the pieces are a little thick on primer due to one previously applied coat that was a lot thicker, and a really thin touch up coat. Hopefully all the pieces still fit together well. I'll find out when I start riveting and there's no going back at this point. As seen below, the garage is a mess with parts everywhere drying out. On to assembly and riveting!! -M


Friday, July 17, 2015

1084.1- Tailcone- p.10-17 step 3 (part 2) and step 4

Tailcone- 1 hr 45 mins (Tailcone 62:23, Empennage 237:55, Total 258:51)
Rivet count: 8 (Total 3,694)

Step 4 actually took place a couple nights ago when my friend C.W. came over and I was showing him around the shop and how everything flows for the build. We assembled the bellcrank assembly and then I let him squeeze a few rivets in. Nothing major as far as progress, but figured I would document it for the build and to keep track of the 15 minutes or so that we spent.

Bellcrank Assembly
I got home from work today in a less than stellar mood. I was hoping a little progress would help, but I was sadly mistaken. I decided to try my theory of waiting for the sun to start to drop before painting. It worked perfectly for controlling heat, but I failed to consider the mosquito population that is out looking for a meal. I even was bit in the face, and let me tell you, it is a lot more painful than one would imagine. The other bit of bad news is that the outflow pressure gauge on my compressor broke. So I won't be able to tell how softly or how hard I'm driving the rivet gun. A weekend trip to Harbor Freight is in order.
I made a big batch of primer tonight, and was able to get all the stiffeners, longerons, the rest of the side skin and one of the top skins. I think I might be able to finish off the priming with just one more batch. I still have the frames/bulkheads, the other side skin, and the other top skin left to go. What I did notice after grabbing the parts when they dried is that some places I didn't get the primer as well as ideal. So I'll say two more small batches, and we are definitely in the clear. -M

Thursday, July 16, 2015

1084- Tailcone- p.10-16 step 3-5

Tailcone- 2 hrs 14 mins (Tailcone 60:38, Empennage 236:10, Total 257:06)
Rivet count: 0 (Total 3,686)

Dimpling is complete! The new dimple die arrived in the mail today. Since I also found out my checkride isn't tomorrow, that meant we had time to get some work in tonight... I started off with all the flanges of the bulkheads and frames, and then finished up the skins . After a dinner break, I was back at the stiffeners with some welcomed help from my wife. I had her hold the stiffeners and move them from the dimpled hole to the undimpled hole while I focused on the actual squeezing of the dimples. It at least felt like it moved along much faster, and a few new blisters might be testament to the fast pace. Needless to say, I thought I was looking at four more hours of dimpling, and it was done in just over two. Now it's just a matter of waiting for an overcast day to get the last of the cleaning and priming accomplished before we get in the full swing of riveting again. -M



Sunday, July 12, 2015

1083.1- Tailcone- p.10-17 step 3 (part 1)

Tailcone- 3 hrs 0 mins (Tailcone 58:24, Empennage 233:56, Total 254:52)
Rivet count: 0 (Total 3,686)

It wasn't as nice of a day as yesterday was. For priming that is. It was a gorgeous blue sky day, but that meant I had to prime parts in the shade under the tree. I will not be doing that again... there was too much dust and bugs to keep track of. From here on out, I'll be waiting until the ideal overcast weather, or I'll just wait until dusk when the sun isn't heating up the metal directly.

Spent about an hour or so cleaning the parts that were ready with acetone, then set up the compressor and parts in the yard. I ended up making two batches of primer to get all the smaller parts, bottom skin, and 75% of the left skin. I still need all the frames/bulkheads, all the stiffeners/longerons, and the two top skins and right skin. Of course this doesn't include the random touchups for paint that didnt apply thick enough on all the pieces. I'm thinking three more batches and we'll be set... Now we just have to wait for the mailman to bring some parts in.. -M



Saturday, July 11, 2015

1083- Tailcone- p.10-16 step 2-3

Tailcone- 3 hrs 43 mins (Tailcone 55:24, Empennage 230:56, Total 251:52)
Rivet count: 0 (Total 3,686)

It was a gorgeous day outside. I thought I'd be able to get all the pieces dimpled and start working on getting things primed up today, but two things happened. First, I severely underestimated how long it takes to dimple thousands of holes. It took nearly two hours just to get the side skins done. I was also able to get the bottom skin and start work on the first of the top skins. Second, my dimple die broke on me...
I tried to round off the sharp edge and see if I could still use it by being careful, but the first dimple I tried didn't come out great and I wasn't about to risk it with 60%+ of the dimples left to go. An internet shopping experience and $40 later, and I'll have a new dimple die in the mail in a few days. I spent the last half hour or so reviewing the plans and marking off the holes that won't get dimpled.

So, three hours of dimpling and I'm not even half way. For every hole on the skins, there will be a hole (or two) that needs dimpling on the substructure frames or stiffeners. So we still have about 4 hours of dimpling left once the new die arrives in the mail. As I marked off what needed dimpling still, I also separated the parts that were ready for priming. I know it will take me at least 4 batches of primer epoxy to get everything done, so it appears I'll at least be able to move forward with priming if the weather tomorrow is as good as it was today. Even so, since I started with the skins instead of the frames, once I do get things primed, I'll only be able to rivet some nutplates while I wait for the remaining parts to get dimpled and primed. Had I started with the frames and stiffeners, then I'd just have to wait to prime and attach the skins,

Also, if ever there was an ad for joining an EAA chapter, this scenario would be it. I knew I was only going to be in MS for a year, and a busy year at that, but I'm sure there's a fellow builder out there that would have gladly lent me a dimple die for a few days while the new one gets shipped. Then again, maybe it's a sign of divine intervention since I'm due for a checkride this week. A sign I should be focused on studies instead of on building... Well, $h!t happens. -M


Friday, July 10, 2015

1082- Tailcone- p.10-15 step 8 & p.10-16 step 1

Tailcone- 4 hrs 48 mins (Tailcone 51:41, Empennage 227:13, Total 248:09)
Rivet count: 0 (Total 3,686)

Scuffing and Countersinking are complete! Three hours of scuffing was quite the test of patience and ensuring I did everything completely. The first hour was from a few nights ago, but I was too tired and didn't post the video. After the scuffing was all complete, we countersunk the AEX tie-down, a stop brace, and the two longerons. We taped off a few holes on the longerons to make sure they were left untouched. Easy work!

Tomorrow, we'll finish up with all the dimpling, and if the weather is good, we'll start cleaning parts in preparation for priming!!! -M



Tuesday, July 7, 2015

1081- Tailcone- p.10-16 step 6-8 & p.10-17 step 1-2

Tailcone- 1 hr 31 mins (Tailcone 46:53, Empennage 222:25, Total 243:21)
Rivet count: 0 (Total 3,686)

As promised, we worked ahead to get the last few parts (bellcrank and battery brace) done. It was a short workday. Cut pieces, finished edges, deburred holes, and even some countersinking. In all of that, I forgot to scuff the parts, so tomorrow, I'll need to be careful around the countersunk holes. Tomorrow I will also be scuffing all of the remaining parts and pieces of the tailcone. Then, I'll go back and finish the countersinking step from last time. When all is done, steps 1-5 (countersinking the longerons and dimpling most of the parts) that I skipped today will finish up the assembly for the tailcone. Afterwards, it will be a matter of finding good weather in order to clean and prime all the parts before starting the riveting process. I feel like I'm moving along fairly quickly, but I know there will be endless hours of riveting those thousand rivets on the outer skins!!


Sunday, July 5, 2015

1080- Tailcone- p.10-15 step 4-9

Tailcone- 3 hrs 12 mins (Tailcone 45:22, Empennage 220:54, Total 241:50)
Rivet count: 0 (Total 3,686) 

After an hour and 40 minutes, we finally finished deburring after spending just under 7 hours over the past three days. Sort of. After all the major dimpling is done, there are still a few more parts that need to be cut, trim, edged, and deburred as well. The tailcone will require over 7 hours of deburring holes. Insane.

After that was done, we continued by scuffing some of the parts so they can be primed later on. We then dimpled those parts as the directions told us to. Also in there was a random step to enlarge a hole with a Unibit so we can attach the Tie-down eye bolt later on. 

Step 8 on this page directs us to countersink a part to accept dimples, but my countersink drill is already set for a #40 rivet. The next time I work on this, I will be going slightly out of order. I plan to go ahead and work on the next group of parts until they are done and ready for scuffing. That way, I can go ahead and scuff all the parts and get everything really dirty with all the dust that gets created. Then I'll countersink the longerons for #40 rivets since that is where I have the drill set to. After that is all done, I'll come back to step 8 and adjust the drill for this depth height. It's one of the few complaints I have about Van's. Some things seem out of order for no apparent reason. However, that's also the same thing that keep it interesting. There's the "blindly follow directions" aspect of building, and there's the "understand and comprehend" aspect of knowing exactly how each little drill, deburr, and clamping fits in to the bigger picture of getting the project done. End ramble. -M


Saturday, July 4, 2015

1079- Tailcone- p.10-15 step 4 (part 2 of 3)

Tailcone- 4 hrs 27 mins (Tailcone 42:10, Empennage 217:42, Total 238:38)
Rivet count: 0 (Total 3,686)

DEBURRING. DEBURRING. MORE DEBURRING...

All 4.5 hrs today were spent deburring. Sadly, we're not even done yet. We managed to get all the skins and odds/ends pieces done. We still have three more frames (1006, 1007, and 1008) and all the J-channel stiffeners (12 total). Otherwise, there's really not a lot to say about today. Just one of the necessary albeit unpleasant tasks that need to be done. I hear it gets worse once we start building the wings and there are many, many repetitive steps for all the structural pieces. At least we're 4.5 hrs closer!! Until tomorrow, when we continue to deburr and then move on to the start of dimpling. -M





Friday, July 3, 2015

1078- Tailcone- p.10-14 step 1-5 & p.10-15 step 1-4

Tailcone- 4 hrs 41 mins (Tailcone 37:43, Empennage 213:15, Total 234:11)
Rivet count: 0 (Total 3,686)

We started off by removing the top skins that we had just attached and match-drilled yesterday. After, we installed two anchor brackets on the longerons with a #12 drill bit, and then we attached the cover plates at the very aft end of the tailcone. We also drilled the nutplate attach holes there.

I worked ever so slightly ahead of the plans by match drilling two of the pieces in the aft end of the tailcone. The plans call for priming and assembling, and then match drilling with #30 and final drilling with #12. I didn't see how it would be possible to get the drill in there once things are riveted, so I drilled them now while it was still possible to use clecos and move the assembly away from the tailcone. We'll see if that comes back to bite me.

We then continued to systematically disassemble the rest of the tailcone. It was crazy to see the workbench completely empty and what used to be the tailcone was now a pile of parts instead of an awesome 3-D creation. We marked off the right side skin prior to removing it and had to cut a piece off of it. Creativity won by clamping the piece down and moving the grinder along the edge that needed to be smoothed instead of moving a whole part. Probably not my smartest moment from a "this is a safe idea" standpoint, but it worked out.

It was then finally time to start deburring. Edges first. Thankfully most of the edges had already been done, so only about 5 or 7 parts needed. Unfortunately, three of those parts were the side skins and bottom skin. Lots of edging after all. The dremel was key for all the hard to reach areas and corners and by opening the garage (sorry for the flooding of light) I was able to have enough space to get the big parts done. 

We finished off by taking 40 minutes just to deburr all the holes on the left side skin. Tomorrow, we'll get the other side skin, the bottom skin, and the rest of the parts (maybe) before the dimpling process begins! -M



Thursday, July 2, 2015

1077- Tailcone- p.10-12 step 8-9 & p.10-13 step 1-7

Tailcone- 4 hrs 21 mins (Tailcone 33:02, Empennage 208:34, Total 229:30)
Rivet count: 0 (Total 3,686)

We started by finishing yesterday's work of match-drilling the stiffeners to the forward top skin. With a limited number of clecos, there was some creative reshuffling to have enough of them to properly match-drill. After, we match-drilled the remaining holes of both top skins to all the frames and longerons.

Next, we spent an hour and a half to fabricate two braces. No clue why it took so long, but they came out looking dang good...! The rest of the work today was spent match drilling the top deck into the longerons, and the remaining spacers, frames, and the two brackets that we just created.

This was the last of the major construction for the tailcone. The next step has us starting to take things apart... which means the arduous dimpling and deburring steps are just around the corner! -M