1091- Tailcone- p.10-22 step 1-3 & p.10-23 step 1-2

Tailcone- 4 hrs 48 mins (Tailcone 87:33, Empennage 263:05, Total 284:01)
Rivet count: 230 (Total 5,321)

This post is actually three days worth of work done a few weeks ago. I'm finally complete with pilot training!!!!!! so I'm catching up on administrative things such as updating this blog!!

In total, the top skin was attached and riveted to the stiffeners, longerons, and frames/bulkheads. That really sums it up! Some of the hardware was attached where the plans called for it. I noticed that I forgot to prime two pieces a few weeks back, so I am going to work ahead to chapter 13 of the wing spars and prime the two pieces along with those from the next chapter before jumping back and finishing up the tailcone with about an hour more of work. -M










This image is here for a question asked on vansairforce.com. Please ignore.